School rebuilding programme missing targets, BBC finds

2 hours ago 3

BBC/ Hazel Shearing Four students basal   successful  the gym astatine  Patchway Community School successful  Bristol. Above them, 2  ceiling panels are missing and cracks person  appeared successful  othersBBC/ Hazel Shearing

The immense bulk of schools connected a authorities rebuilding programme successful England are waiting for builders, according to a Freedom of Information request.

Hundreds of aged and leaky schoolhouse buildings successful England inactive don’t person builders assigned to them - adjacent though they’re connected a flagship authorities rebuilding programme, the BBC has found.

More than 500 schools are connected the scheme, but by this summertime contracts had been awarded to operation companies to rebuild conscionable 62 of them.

The BBC has been looking into wherefore targets are being missed. Industry experts person told america operation companies are tense astir taking connected contracts successful lawsuit costs transcend their budgets.

But the Department for Education (DfE) says the programme is connected way and forecasts were made earlier precocious ostentation deed the operation industry.

The School Rebuilding Programme, announced successful 2020, aims to rebuild oregon refurbish astir 500 schools successful a decade.

Construction was owed to commencement successful 2021 astatine a complaint of astir 50 schools per year.

However, according to the National Audit Office (NAO), the DfE forecast past twelvemonth that it would implicit less projects than it had initially planned.

The BBC has recovered 23 schools person been completed truthful acold and a further 490 are inactive waiting. Most bash not yet person builders connected board.

The DfE originally projected that 83 contracts would beryllium awarded by March 2023.

However, its effect to a BBC Freedom of Information (FOI) petition revealed lone 62 had been issued by June 2024.

BBC/ Gemma Laister A antheral   wearing a reddish  polo garment  sticks yellowish  and achromatic  portion    on  the borderline   of a portion   of carpet successful  a corridor astatine  Patchway Community School.BBC/ Gemma Laister

Patchway Community School's rebuild has been delayed by astatine slightest a year, according to the caput of its trust.

Patchway Community School successful Bristol was selected for the School Rebuilding Programme successful 2021, but is inactive waiting to beryllium assigned a operation company.

"Sometimes erstwhile it's raining, the airy malfunctions and you tin hardly spot anything," said Year 8 pupil Faizah.

"When we play games similar dodgeball oregon basketball, immoderate of the balls get stuck up successful the extortion due to the fact that of the holes," said Logan, besides successful Year 8.

Dave Baker, the main enforcement serviceman of The Olympus Academy Trust, which runs Patchway, said the cracked ceiling successful the schoolhouse gym, similar different areas of deterioration and tear, was "not worthy replacing, due to the fact that the full happening is going to beryllium knocked down wrong the adjacent 2 years".

BBC/ Hazel Shearing Dave Baker, wearing a bluish  suit, achromatic  garment  and orangish  bow-tie, stands successful  the playground astatine  Patchway School, successful  beforehand   of immoderate   of the buildings that volition  beryllium  demolishedBBC/ Hazel Shearing

Dave Baker says Patchway is seen arsenic the "poor neighbour" of others successful the spot that person been built successful caller years.

He said the rebuilding process had been delayed by astatine slightest a year, aft a institution that had signed up to rebuild Patchway pulled out.

"The contractors, it seems, felt that they couldn't present the gathering to the specification for the wealth that was available. That's our mentation of what happened," helium said.

"I consciousness that determination are young radical and their families who person been fto down - and that’s not OK."

Mr Baker present hopes to person a caller declaration successful spot successful the coming weeks, and a caller schoolhouse with "the champion facilities successful the area" successful 2027.

Building institution Wates told the BBC it worked "extensively" with the DfE and had provided plan services for Patchway, but the DfE "decided connected this juncture not to proceed with Wates for the gathering work".

BBC/ Gemma Laiser A lopsided picnic seat  connected  a spot  of writer  extracurricular  1  of the buildings astatine  Patchway Community School, thought   to person  been constructed successful  the 1950s.BBC/ Gemma Laiser

All barroom 1 of Patchway Community School's buildings, which Mr Baker thinks day backmost to the 1950s, are acceptable to beryllium demolished.

Rebecca Larkin, from the Construction Products Association, which represents manufacturers, said portion a lag betwixt the announcement of the School Rebuilding Programme and getting spades successful the crushed was to beryllium expected, it was inactive moving behind.

"It is not coming done arsenic rapidly oregon connected the docket that was primitively promised by the government," she said, adding that she would person expected astir 100 contracts to person been awarded by now.

Ms Larkin said precocious ostentation whitethorn person made gathering companies "reticent" to instrumentality connected contracts.

BBC/ Hazel Shearing Rebecca Larkin wears a achromatic  T-shirt with a metallic  necklace. It is simply a sunny time  and she stands connected  the thoroughfare  extracurricular  the Department for Education successful  London.BBC/ Hazel Shearing

Rebecca Larkin says ostentation has soared successful the operation manufacture since the Covid pandemic.

"Construction contractors typically run connected precise tiny margins, truthful if they motion up to a declaration and past prices emergence during the operation work, determination is precise small country for manoeuvre," she said.

"Given that determination are fixed superior budgets successful each authorities departments, determination is precise small country for them to manoeuvre arsenic well, truthful you're successful a benignant of Catch-22 situation."

Ms Larkin said updates connected the programme were "very infrequent".

Extra backing would help, she said, but the DfE was competing with different authorities departments for bigger budgets.

Others told the BBC the caller illness of operation institution ISG, which had already started enactment connected astatine slightest 1 schoolhouse connected the School Rebuilding Programme, could marque it adjacent harder for the DfE to find companies to instrumentality connected the work.

The schools connected the School Rebuilding Programme are those the DfE has deemed arsenic being astir successful need.

However, the NAO study past twelvemonth said backing levels successful England had contributed to the "deterioration" of the wider schoolhouse property - and 24,000 schoolhouse buildings (38% of the total) were beyond their archetypal beingness design.

James Ludlow, main astatine Joseph Leckie Academy successful Walsall, said helium spent £10,000 of the school's fund refurbishing its 1930s schoolhouse hallway this summertime due to the fact that helium became "fed up" with the peeling overgarment and damp.

"We're having to walk a batch of wealth connected patching things up," helium said.

The NAO study besides said the "slower than planned" advancement of the School Rebuilding Programme was "largely owed to operation providers not taking up contracts".

It said the DfE had "taken steps to code these issues, including by changing its attack to task backing argumentation to bespeak marketplace conditions".

The DfE told the BBC the programme was connected track, and its archetypal forecasts were made earlier events including Russia’s penetration of Ukraine affected manufacture prices.

It said schools instrumentality an mean of 2 to 5 years to build, and that immoderate signifier of enactment had started astatine conscionable nether fractional of the projects - though it did not specify what benignant of work.

In a statement, acquisition curate Stephen Morgan said the authorities "inherited a schoolhouse property successful request of urgent repair... and without a broad plan" - and that this would "not beryllium a speedy fix".

Additional reporting by Kevin Core.